Original Schedule:
Oct 14th: have exact coverage of the report figured out
Oct 30th: have report outline done
Nov 7th: be near completion of the demo
Nov 18th: be finished demo and report
Updated Schedule:
Completed: have exact coverage of the report figured out
Nov 8th: have report outline and 5 pages of the report complete
Nov 15: be near completion of the demo and 7 pages of the report complete
Nov 18: be finished demo and report
-
Featured
Project Proposal
My project is on binaural audio. Binaural audio is three dimensional sound, where the listener typically has headphones on that can replicate where audio is heard, above, below, behind, etc (see: https://www.youtube.com/watch?v=IUDTlvagjJA as a good example). The concept has been around a while and has been explored quite a bit. Though it has never caught… Read more
-
Project Demo
-
Project Update
After some consideration the report coverage has been changed. When covering strictly binaural audio there is not much documented about algorithms, more is written about how it is recorded, the equipment used, and why its failed. These are fine on their own for a report but not for this class, maybe that can be saved… Read more